Build Started on Tuesday 5th of September 2006
This project in Grange Randalstown was undertaken with two Joiners, two Labourers, the project got underway on Tuesday 5th of September 2006.

(No Photo Available)

Thursday 7th of September 2006
Two days later the project is well underway, both gable walls have been completed with Novabrik - with only the Peaks to be completed.

grange mccavana 1

Monday 11th of September 2006
Both gable walls are now 100% complete. The front of the building has been completed to ground floor at head height. The rear of the house has not been started yet. So far there has been 5 days of work (7th,8th,9th,10th and 11th).

11th

Off Site.
Unfortunately the labourers and joiners got called to another site from 12/09/06 to 26/09/06. The photo on the 21st of September below shows no progress from the 11th.

21st no progress

Tuesday 26th of September.
The labourers and joiners return to site, and resume work.

(No Photo Available).

Wednesday 27th of September.
The front of he development is 100% complete, and the rear is 70% complete. The rear of the job was completed later that day.

27th

Friday 06th of October.
Our photographer returned to site to view the project with the scaffolding removed. Total number of working days - 7 working days (7th,8th,9th,10th and 11th of September) and (26th,27th of September).